This skill provides portfolio-level risk identification, assessment, correlation, and mitigation planning with RAID log maintenance across projects.

npx playbooks add skill lerianstudio/ring --skill risk-management

Review the files below or copy the command above to add this skill to your agents.

Files (1)
SKILL.md
8.0 KB
---
name: ring:risk-management
description: |
  Portfolio-level risk management skill for identifying, assessing, and mitigating
  risks across multiple projects. Maintains RAID logs and tracks risk responses.

trigger: |
  - Need portfolio risk assessment
  - Creating or updating RAID log
  - Risk response planning
  - Risk correlation analysis

skip_when: |
  - Single project risk → handle in project scope
  - Financial risk only → use ring-finops-team
  - Technical risk in code → use ring:qa-analyst

related:
  complementary: [portfolio-planning, project-health-check]
---

# Risk Management Skill

Systematic portfolio-level risk identification, assessment, and mitigation.

## Purpose

This skill provides a framework for:
- Portfolio risk identification
- Risk assessment and scoring
- Risk correlation analysis
- Mitigation planning
- RAID log management

---

## Prerequisites

Before risk assessment, ensure:

| Prerequisite | Required For | Source |
|--------------|--------------|--------|
| Project risk registers | Risk aggregation | Project managers |
| Historical risk data | Pattern identification | Previous projects |
| Stakeholder input | Risk identification | Key stakeholders |
| Impact criteria | Risk scoring | PMO standards |

---

## Risk Management Gates

### Gate 1: Risk Identification

**Objective:** Identify all portfolio-level risks

**Actions:**
1. Collect project-level risks
2. Identify cross-project risks
3. Capture portfolio-level risks
4. Document assumptions and dependencies

**Risk Categories:**

| Category | Examples |
|----------|----------|
| **Strategic** | Market changes, competition, regulation |
| **Resource** | Key person departure, skill shortage, capacity |
| **Technical** | Technology obsolescence, integration, security |
| **Financial** | Budget cuts, cost overruns, currency |
| **Schedule** | Dependencies, delays, scope creep |
| **External** | Vendor, regulatory, geopolitical |

**Output:** `docs/pmo/{date}/risk-register.md`

---

### Gate 2: Risk Assessment

**Objective:** Assess probability and impact of each risk

**Actions:**
1. Assess probability (1-5 scale)
2. Assess impact (1-5 scale)
3. Calculate risk score (P x I)
4. Assign severity level

**Risk Severity Matrix:**

See [shared-patterns/pmo-metrics.md](../shared-patterns/pmo-metrics.md) for risk severity matrix.

| Impact / Likelihood | Low (1-2) | Medium (3) | High (4-5) |
|---------------------|-----------|------------|------------|
| **High (4-5)** | Medium | High | Critical |
| **Medium (3)** | Low | Medium | High |
| **Low (1-2)** | Low | Low | Medium |

**Output:** `docs/pmo/{date}/risk-assessment.md`

---

### Gate 3: Risk Correlation

**Objective:** Identify correlated risks across portfolio

**Actions:**
1. Identify shared risk factors
2. Map risk dependencies
3. Calculate compound risk exposure
4. Flag correlated critical risks

**Correlation Types:**

| Type | Description | Action |
|------|-------------|--------|
| **Shared cause** | Same root cause affects multiple projects | Mitigate root cause |
| **Sequential** | One risk triggers another | Plan cascade response |
| **Resource** | Same resource/skill shortage | Diversify or hire |
| **Vendor** | Same vendor dependency | Diversify suppliers |

**Output:** `docs/pmo/{date}/risk-correlation.md`

---

### Gate 4: Response Planning

**Objective:** Create mitigation plans for significant risks

**Actions:**
1. Select response strategy per risk
2. Define mitigation actions
3. Assign owners and dates
4. Allocate contingency

**Response Strategies:**

See [shared-patterns/pmo-metrics.md](../shared-patterns/pmo-metrics.md) for response types.

| Response | When to Use | Example |
|----------|-------------|---------|
| **Avoid** | Risk unacceptable, can change scope | Remove risky feature |
| **Transfer** | Risk better managed by others | Insurance, outsource |
| **Mitigate** | Reduce probability or impact | Testing, redundancy |
| **Accept** | Cost of mitigation > impact | Document and monitor |

**Output:** `docs/pmo/{date}/risk-response-plan.md`

---

### Gate 5: RAID Log Update

**Objective:** Maintain comprehensive RAID log

**Actions:**
1. Update Risk section
2. Update Assumptions section
3. Update Issues section
4. Update Dependencies section

**RAID Categories:**

| Category | Contents | Review Frequency |
|----------|----------|------------------|
| **R**isks | Potential future issues | Weekly |
| **A**ssumptions | Believed true, not verified | At milestones |
| **I**ssues | Current problems requiring action | Daily |
| **D**ependencies | External inputs/outputs | Weekly |

**Output:** `docs/pmo/{date}/raid-log.md`

---

## Anti-Rationalization Table

See [shared-patterns/anti-rationalization.md](../shared-patterns/anti-rationalization.md) for universal anti-rationalizations.

### Risk-Specific Anti-Rationalizations

| Rationalization | Why It's WRONG | Required Action |
|-----------------|----------------|-----------------|
| "We've seen this risk before" | Context changes. Each occurrence needs fresh assessment. | **Assess current state** |
| "Low probability, don't document" | Low probability × high impact = significant risk. | **Document ALL identified risks** |
| "Team will handle it" | Unplanned handling = crisis response. Plan required. | **Document response plan** |
| "Risk register is up to date" | Registers decay. Continuous validation required. | **Validate at every review** |
| "That won't happen" | Famous last words. Document and monitor. | **Document ALL risks** |

---

## Pressure Resistance

See [shared-patterns/pressure-resistance.md](../shared-patterns/pressure-resistance.md) for universal pressure scenarios.

### Risk-Specific Pressures

| Pressure Type | Request | Agent Response |
|---------------|---------|----------------|
| "Don't include that risk, it will worry people" | "Risk transparency is non-negotiable. Including with mitigation plan to provide balanced view." |
| "That's been mitigated, remove it" | "Mitigated risks remain in register until formally closed with evidence. Updating status, not removing." |
| "Risk assessment takes too long" | "Unassessed risks cause larger delays when they materialize. Completing assessment." |

---

## Blocker Criteria - STOP and Report

**ALWAYS pause and report blocker for:**

| Situation | Required Action |
|-----------|-----------------|
| Critical risk without mitigation plan | STOP. Escalate. Risk cannot be accepted without plan. |
| Multiple correlated critical risks | STOP. Report compound exposure. Wait for portfolio decision. |
| Risk owner not identified | STOP. Unowned risks are unmanaged. Require owner assignment. |
| Assumption invalidated | STOP. Trigger re-planning based on new reality. |

---

## Output Format

### Risk Summary

```markdown
# Portfolio Risk Summary - [Date]

## Risk Overview

| Metric | Value |
|--------|-------|
| Total Risks | N |
| Critical | N |
| High | N |
| Medium | N |
| Low | N |
| Mitigations Defined | N/N |
| Overdue Actions | N |

## Top Risks

| ID | Risk | Severity | Owner | Status |
|----|------|----------|-------|--------|
| R-001 | [Description] | Critical/High | [Owner] | [Status] |

## Risk Correlations

| Correlation | Risks | Combined Exposure | Action |
|-------------|-------|-------------------|--------|
| [ID] | [Risk IDs] | [Exposure] | [Action] |

## RAID Summary

| Category | Total | New | Closed | Overdue |
|----------|-------|-----|--------|---------|
| Risks | N | N | N | N |
| Assumptions | N | N | N | N |
| Issues | N | N | N | N |
| Dependencies | N | N | N | N |

## Recommendations

1. [Recommendation with rationale]
2. [Recommendation with rationale]

## Decisions Required

1. [Decision needed: Accept/Mitigate/Avoid risk X]
```

---

## Execution Report

Base metrics per [shared-patterns/execution-report.md](../shared-patterns/execution-report.md):

| Metric | Value |
|--------|-------|
| Analysis Date | YYYY-MM-DD |
| Scope | [Portfolio/Projects] |
| Duration | Xh Ym |
| Result | COMPLETE/PARTIAL/BLOCKED |

### Risk-Specific Details

| Metric | Value |
|--------|-------|
| risks_identified | N |
| risks_by_severity | C/H/M/L |
| mitigation_plans | N |
| overdue_actions | N |

Overview

This skill delivers portfolio-level risk management for identifying, assessing, and mitigating risks across multiple projects. It centralizes RAID log maintenance, enforces risk gates, and produces standardized outputs like risk registers, correlation maps, and response plans. Use it to surface cross-project exposures and drive timely mitigation and escalation.

How this skill works

The skill ingests project risk registers, historical risk data, and stakeholder input to build a consolidated portfolio view. It runs five gates: identification, assessment (probability × impact scoring), correlation analysis, response planning, and RAID log updates. Each gate produces date-stamped artifacts and metrics to support decisions and escalations.

When to use it

  • At portfolio planning and quarterly reviews to aggregate project risks
  • When onboarding new projects to capture shared dependencies and assumptions
  • After significant changes (scope, vendor, regulation) that may affect multiple projects
  • Before executive decision points to prepare consolidated mitigation options
  • When overdue actions or unowned risks appear and require STOP-and-report

Best practices

  • Collect project-level registers and validate assumptions before assessment
  • Score probability and impact consistently using a 1–5 scale and document rationale
  • Detect and flag correlated risks early to avoid compound exposure
  • Assign clear owners and target dates for every mitigation action
  • Keep RAID log entries current and retain mitigated risks until formally closed

Example use cases

  • Identify a shared vendor failure risk affecting three projects and create a diversification plan
  • Aggregate budget and schedule overruns to prioritize contingency allocation across the portfolio
  • Detect a single-skill bottleneck and trigger hiring or upskilling to reduce resource risk
  • Produce a portfolio risk summary for the PMO and executive steering committee
  • Stop and escalate when a critical risk lacks an owner or mitigation plan

FAQ

What inputs does the skill require?

Project risk registers, historical risk records, stakeholder input, and impact criteria from PMO standards.

How are risk severity and scores determined?

Probability and impact are each scored 1–5; risk score equals probability × impact and maps to severity via the defined severity matrix.