This skill helps you identify, analyze, and prioritize project risks and craft mitigation strategies to improve chances of project success.

npx playbooks add skill aj-geddes/useful-ai-prompts --skill risk-assessment

Review the files below or copy the command above to add this skill to your agents.

Files (1)
SKILL.md
10.0 KB
---
name: risk-assessment
description: Identify, analyze, and prioritize project risks using qualitative and quantitative methods. Develop mitigation strategies to minimize impact and maximize project success probability.
---

# Risk Assessment

## Overview

Risk assessment is a systematic process of identifying potential threats to project success and developing strategies to mitigate, avoid, or accept them.

## When to Use

- Project initiation and planning phases
- Before major milestones or decisions
- When introducing new technologies
- Third-party dependencies or integration
- Organizational or resource changes
- Budget or timeline constraints
- Regulatory or compliance concerns

## Instructions

### 1. **Risk Identification Techniques**

```python
# Risk identification framework

class RiskIdentification:
    RISK_CATEGORIES = {
        'Technical': [
            'Technology maturity',
            'Integration complexity',
            'Performance requirements',
            'Security vulnerabilities',
            'Data integrity'
        ],
        'Resource': [
            'Team skill gaps',
            'Staff availability',
            'Budget constraints',
            'Equipment/infrastructure',
            'Vendor availability'
        ],
        'Schedule': [
            'Unrealistic deadlines',
            'Dependency delays',
            'Scope creep',
            'Approval delays',
            'Resource conflicts'
        ],
        'External': [
            'Regulatory changes',
            'Market conditions',
            'Vendor stability',
            'Political/economic factors',
            'Natural disasters'
        ],
        'Organizational': [
            'Stakeholder misalignment',
            'Priority changes',
            'Organizational restructuring',
            'Politics/conflicts',
            'Requirement changes'
        ]
    }

    @staticmethod
    def brainstorm_risks(project_context):
        """
        Facilitated brainstorming session to identify risks
        """
        risks = []
        for category, risk_types in RiskIdentification.RISK_CATEGORIES.items():
            for risk_type in risk_types:
                risks.append({
                    'category': category,
                    'description': risk_type,
                    'identified_by': [],
                    'probability': None,
                    'impact': None
                })

        return risks

    @staticmethod
    def analyze_assumptions_as_risks(assumptions):
        """
        Convert project assumptions into potential risks
        """
        assumption_risks = []
        for assumption in assumptions:
            assumption_risks.append({
                'risk_type': 'Assumption Violation',
                'description': f"Assumption '{assumption}' is invalid",
                'trigger': f"Evidence that {assumption} is false",
                'impact': 'High' if assumption.startswith('Critical') else 'Medium'
            })

        return assumption_risks
```

### 2. **Risk Analysis Matrix**

```javascript
// Qualitative and quantitative risk analysis

class RiskAnalysis {
  constructor() {
    this.riskMatrix = [];
    this.priorityMap = [];
  }

  // Probability scale 1-5
  static PROBABILITY = {
    1: { name: 'Very Low', percentage: 0.1, color: 'Green' },
    2: { name: 'Low', percentage: 0.3, color: 'Green' },
    3: { name: 'Medium', percentage: 0.5, color: 'Yellow' },
    4: { name: 'High', percentage: 0.7, color: 'Orange' },
    5: { name: 'Very High', percentage: 0.9, color: 'Red' }
  };

  // Impact scale 1-5
  static IMPACT = {
    1: { name: 'Negligible', value: 1, scope: 'Minor inconvenience' },
    2: { name: 'Minor', value: 10, scope: 'Some delay or cost' },
    3: { name: 'Moderate', value: 100, scope: 'Significant delay or cost' },
    4: { name: 'Major', value: 1000, scope: 'Critical failure risk' },
    5: { name: 'Catastrophic', value: 10000, scope: 'Project cancellation' }
  };

  analyzeRisk(risk) {
    const probability = this.PROBABILITY[risk.probability];
    const impact = this.IMPACT[risk.impact];

    // Risk Score = Probability × Impact
    const riskScore = risk.probability * risk.impact;

    // Risk Exposure = Probability × Financial Impact
    const riskExposure = probability.percentage * impact.value;

    return {
      riskId: risk.id,
      riskScore,
      riskExposure,
      priority: this.calculatePriority(riskScore),
      severity: this.calculateSeverity(riskScore),
      mitigationUrgency: riskExposure > 100 ? 'Immediate' : 'Planned'
    };
  }

  calculatePriority(riskScore) {
    if (riskScore >= 16) return 'Critical';
    if (riskScore >= 12) return 'High';
    if (riskScore >= 6) return 'Medium';
    if (riskScore >= 2) return 'Low';
    return 'Very Low';
  }

  calculateSeverity(riskScore) {
    return {
      score: riskScore,
      rating: this.calculatePriority(riskScore),
      responseNeeded: riskScore >= 12
    };
  }

  // Risk Matrix
  createRiskMatrix(risks) {
    const matrix = {
      critical: [],
      high: [],
      medium: [],
      low: [],
      veryLow: []
    };

    risks.forEach(risk => {
      const analysis = this.analyzeRisk(risk);
      const priority = analysis.priority.toLowerCase();

      if (matrix[priority]) {
        matrix[priority].push({
          ...risk,
          ...analysis
        });
      }
    });

    return matrix;
  }
}
```

### 3. **Risk Response Planning**

```yaml
Risk Response Strategies:

Risk 1: Integration Delay with Third-Party API
  Probability: High (4/5)
  Impact: Major (4/5)
  Risk Score: 16 (Critical)

  Response Strategy: MITIGATION

  Actions:
    - Engage vendor early in planning (Week 1)
    - Develop fallback solution in parallel (Week 2-4)
    - Allocate 20% more development time (buffer)
    - Weekly sync with vendor team
    - Performance testing starts Month 2

  Owner: Technical Lead
  Budget Impact: +$15,000
  Timeline: 6 weeks vs. 4 weeks planned

---

Risk 2: Scope Creep from Stakeholders
  Probability: High (4/5)
  Impact: Moderate (3/5)
  Risk Score: 12 (High)

  Response Strategy: AVOIDANCE & MITIGATION

  Actions:
    - Establish change control process (Week 1)
    - Lock requirements for Phase 1 (Week 2)
    - Monthly scope review meetings
    - Create feature backlog for Phase 2
    - Strict change request evaluation criteria

  Owner: Project Manager
  Cost of Avoidance: 5 hours/week PM time
  Alternative: Accept 2-week timeline extension

---

Risk 3: Key Person Departure
  Probability: Medium (3/5)
  Impact: Major (4/5)
  Risk Score: 12 (High)

  Response Strategy: MITIGATION & CONTINGENCY

  Actions:
    - Knowledge transfer documentation (ongoing)
    - Cross-training second developer (Week 1)
    - Maintain up-to-date runbooks
    - Competitive salary review (HR)
    - Mentoring program setup

  Owner: HR Manager
  Contingency: Hire contractor within 1 week
  Estimated Cost: $20,000
```

### 4. **Risk Monitoring & Control**

```javascript
// Risk tracking and monitoring dashboard

class RiskMonitoring {
  constructor() {
    this.risks = [];
    this.triggers = [];
    this.escalations = [];
  }

  createRiskRegister(risks) {
    return risks.map((risk, index) => ({
      id: `RK-${String(index + 1).padStart(3, '0')}`,
      description: risk.description,
      category: risk.category,
      probability: risk.probability,
      impact: risk.impact,
      riskScore: risk.probability * risk.impact,
      responseStrategy: risk.strategy,
      owner: risk.owner,
      status: 'Active',
      triggers: risk.triggers,
      contingencyPlan: risk.contingency,
      createdDate: new Date(),
      lastReviewDate: new Date(),
      closeDate: null
    }));
  }

  identifyRiskTriggers(risk) {
    return {
      riskId: risk.id,
      triggers: [
        {
          trigger: 'Vendor communication delay >1 week',
          indicator: 'No response from vendor',
          escalationAction: 'Contact vendor PM, evaluate alternatives'
        },
        {
          trigger: 'Team member absence >3 days',
          indicator: 'Unplanned time off',
          escalationAction: 'Activate cross-training plan'
        },
        {
          trigger: 'Performance test fails baseline',
          indicator: 'Response time > 500ms',
          escalationAction: 'Emergency optimization sprint'
        }
      ],
      reviewFrequency: 'Weekly standup'
    };
  }

  monitorRisks(riskRegister) {
    const statusReport = {
      timestamp: new Date(),
      summary: {
        total: riskRegister.length,
        active: riskRegister.filter(r => r.status === 'Active').length,
        mitigated: riskRegister.filter(r => r.status === 'Mitigated').length,
        closed: riskRegister.filter(r => r.status === 'Closed').length
      },
      criticalRisks: riskRegister.filter(r => r.riskScore >= 16),
      highRisks: riskRegister.filter(r => r.riskScore >= 12 && r.riskScore < 16),
      triggeredRisks: riskRegister.filter(r => r.triggered === true)
    };

    return statusReport;
  }
}
```

## Best Practices

### ✅ DO
- Identify risks early in project planning
- Involve diverse team members in risk identification
- Quantify risk impact when possible
- Prioritize based on risk score and exposure
- Develop specific mitigation plans
- Assign clear risk ownership
- Monitor triggers regularly
- Review and update risk register monthly
- Document lessons learned from realized risks
- Communicate risks transparently to stakeholders

### ❌ DON'T
- Wait until problems occur to identify risks
- Assume risks will not materialize
- Treat all risks as equal priority
- Plan mitigation without clear trigger conditions
- Ignore early warning signs
- Make risk management a one-time activity
- Skip contingency planning for critical risks
- Hide negative risks from stakeholders
- Eliminate all risk (impossible and uneconomical)
- Blame individuals for realized risks

## Risk Management Tips

- Risk ownership motivates accountability
- Regular risk review prevents surprises
- Risk response should be cost-effective
- Some risk tolerance is healthy and necessary
- Documented risks are easier to manage

Overview

This skill identifies, analyzes, and prioritizes project risks using both qualitative and quantitative methods, then defines mitigation and contingency plans to reduce impact. It helps teams convert assumptions into risks, score and rank threats, and create actionable response strategies tied to owners, timelines, and budgets. The output focuses on measurable risk exposure and clear monitoring triggers to keep projects on track.

How this skill works

The skill walks through risk identification across technical, resource, schedule, external, and organizational categories, including facilitated brainstorming and assumption analysis. It scores risks using a 1–5 probability and impact scale, computes risk score and exposure, and maps results into priority bands (Critical, High, Medium, Low). Finally, it produces response plans, owners, timeboxes, and a living risk register with triggers and monitoring reports.

When to use it

  • Project initiation and planning
  • Before major milestones or go/no-go decisions
  • When adopting new technology or third-party integrations
  • During organizational or resource changes
  • If budget, timeline, or compliance risk emerges
  • Before accepting assumptions as facts

Best practices

  • Identify risks early and involve diverse stakeholders
  • Quantify impact where possible and score consistently
  • Prioritize by risk score and financial exposure, not by instinct
  • Assign clear owners, deadlines, and trigger conditions
  • Keep a living risk register and review monthly
  • Define mitigation and contingency separately with estimated costs

Example use cases

  • Assess integration risk for a vendor API and plan fallbacks with owner and budget
  • Convert project assumptions into risk entries and set triggers for early detection
  • Score and prioritize a backlog of identified risks into Critical/High/Medium/Low buckets
  • Create mitigation and contingency actions for key-person departure and track cross-training progress
  • Produce a weekly risk status report showing critical and triggered risks for stakeholders

FAQ

How is risk score calculated?

Risk score is probability × impact using a 1–5 scale; higher scores drive higher priority bands.

When should I move from mitigation to contingency?

Use defined triggers (e.g., vendor delay >1 week, failed performance baseline) to activate contingency; monitor triggers weekly.